The Challenge

A TC4 diagnostic housing with 1.2 mm walls kept warping at the customer's previous supplier — rejected lots delayed their FDA validation schedule, and they needed ±0.01 mm on bearing bores.

Our Solution

We re-sequenced the process: rough machining, stress-relief aging, then finishing with custom soft jaws and low-heat parameters. Ultrasonic cleaning, passivation and laser serial numbers completed the package, with FAI report on the first article.

The Result

The first article passed inspection at once. The housing now ships 2,000 pcs/year in quarterly batches, and lead time dropped from 18 to 12 days after fixturing was finalized.